How an electrician talks about the sheet. Same words the takeoff uses.

AFF
Above finished floor. Used when a device height is noted on the sheet. Drop = ceiling height minus AFF.
Assembly
The kit behind a counted device: whip, hangers, T-bar clips, box, connectors, fittings — not just the fixture.
Bid letter
The recap you stamp and send. Overhead, profit, allowances. Not a second copy of the BOM.
BOM
Bill of materials. Excel-style grid of every line: qty, unit, material, hours, extension.
Branch
Device-to-device pipe on a circuit, after the homerun lands.
Calibrate
Set feet-per-drawing-point on a known dimension or the graphic scale bar. No scale, no footage.
Connector
EMT connector at a box. Typically two per homerun (into the box and into the panel).
Takeoff
Devices and fixtures on the plan sheets. One type across lighting and power plans.
Coupling
Joins 10 ft sticks of EMT. Count = footage / 10, plus waste.
Demo
Removal. (E) on a demo sheet is labor to take out, not new material.
Derived
Fittings, drops, and footage calculated from counted devices and measured pipe. Not a glyph on the plan.
Drop
Plan-hidden vertical: typically 8.5 ft at a receptacle, 6.5 ft at a switch, unless AFF is noted.
EA
Each. Unit for devices, boxes, fittings sold as pieces.
Elbow
90° EMT bend. Conduit is pulled on 90s, not curves.
EMT
Electrical metallic tubing. Raceway. Sized 1/2", 3/4", 1", 2" and up.
Existing-to-remain
Drawn but not new work. (E) is excluded from new-work quantities.
Feeder
Pipe and wire from a distribution board to a panel. One-line callouts stay open until you measure the riser.
Fill
Conductors in a pipe. 3#12 + ground in 3/4" EMT is a typical lighting homerun.
Fixture quote
Package price from the lighting vendor. Paste it. We do not invent a troffer price.
GFCI
Ground-fault receptacle. Counted as its own type when the legend says so.
Hanger / strap
Support for conduit. Typical 3/4" EMT strap every 10 ft.
Homerun
Pipe from the last device back to the panel. Loops between fixtures are the circuit, not extra EMT.
J-box
Junction box. Some marks are column bubbles — confirm vs the legend before you count them as boxes.
Kind
BOM column: counted (on the sheet) vs derived (from the recipe).
Labor rate
Your $/hr. Hours come from assemblies. You set the rate. Occupied / demo can apply a factor.
Legend
The project symbol list. It wins over a generic catalog. Teach a missed mark once.
LF
Linear feet. Raceway, wire, track, cable.
Luminaire schedule
Catalog (type and description). The lighting plan is the takeoff. Fixture dollars stay open until quoted.
MC whip
Metal-clad fixture whip. Usually 6 ft on a T-bar hang, fixture to box.
Named revision
A snapshot of the takeoff. Original vs this takeoff stay. Re-run does not wipe edited cells.
OFCI
Owner-furnished, contractor-installed. Material may be $0. Labor still exists. Do not hide it.
One-line
Riser diagram. Gear and feeder spec. It does not invent pipe length on the floor plan.
Panel schedule
Breaker and load list. Catalog, not a device count on the floor.
Raceway
The pipe: EMT, PVC, GRC. Plus couplings, connectors, straps, elbows, wire.
Recap
Bid summary: material, labor, quoted fixtures, misc, overhead, profit.
RFQ
Request for quote. Export the BOM in a file a distributor can upload.
Scale
Feet per drawing point. Confirm on the title-block scale and the bar.
Shop book
Your labor rate, vendor nets, and cell edits saved for the next job. Restore catalog defaults any time.
Stamp
Marks the letter as the print version. Cells stay editable. Change a qty and the stamp drops.
Strap
Conduit support. See hanger.
T-bar
Lay-in grid ceiling. The fixture is the box. Extra hangers only when the spec asks. Earthquake clips when the note says so.
Takeoff
The count: devices by type, measured raceway, derived fittings. Not the priced letter.
Teach
Click a missed glyph, name it, reuse that type on this job.
THHN
Building wire. Sized with the circuit tag (#12, #10, #8…) plus ground.
UNKNOWN
A blank material price. It stays open. It is not $0. Stamp is blocked until the quote is pasted.
Waste
Raceway only, typically 10%. Not applied to counted devices.
Whip
MC or FMC from the fixture to the box. Usually 6 ft on T-bar.