How an electrician talks about the sheet. Same words the takeoff uses.
- AFF
- Above finished floor. Used when a device height is noted on the sheet. Drop = ceiling height minus AFF.
- Assembly
- The kit behind a counted device: whip, hangers, T-bar clips, box, connectors, fittings — not just the fixture.
- Bid letter
- The recap you stamp and send. Overhead, profit, allowances. Not a second copy of the BOM.
- BOM
- Bill of materials. Excel-style grid of every line: qty, unit, material, hours, extension.
- Branch
- Device-to-device pipe on a circuit, after the homerun lands.
- Calibrate
- Set feet-per-drawing-point on a known dimension or the graphic scale bar. No scale, no footage.
- Connector
- EMT connector at a box. Typically two per homerun (into the box and into the panel).
- Takeoff
- Devices and fixtures on the plan sheets. One type across lighting and power plans.
- Coupling
- Joins 10 ft sticks of EMT. Count = footage / 10, plus waste.
- Demo
- Removal. (E) on a demo sheet is labor to take out, not new material.
- Derived
- Fittings, drops, and footage calculated from counted devices and measured pipe. Not a glyph on the plan.
- Drop
- Plan-hidden vertical: typically 8.5 ft at a receptacle, 6.5 ft at a switch, unless AFF is noted.
- EA
- Each. Unit for devices, boxes, fittings sold as pieces.
- Elbow
- 90° EMT bend. Conduit is pulled on 90s, not curves.
- EMT
- Electrical metallic tubing. Raceway. Sized 1/2", 3/4", 1", 2" and up.
- Existing-to-remain
- Drawn but not new work. (E) is excluded from new-work quantities.
- Feeder
- Pipe and wire from a distribution board to a panel. One-line callouts stay open until you measure the riser.
- Fill
- Conductors in a pipe. 3#12 + ground in 3/4" EMT is a typical lighting homerun.
- Fixture quote
- Package price from the lighting vendor. Paste it. We do not invent a troffer price.
- GFCI
- Ground-fault receptacle. Counted as its own type when the legend says so.
- Hanger / strap
- Support for conduit. Typical 3/4" EMT strap every 10 ft.
- Homerun
- Pipe from the last device back to the panel. Loops between fixtures are the circuit, not extra EMT.
- J-box
- Junction box. Some marks are column bubbles — confirm vs the legend before you count them as boxes.
- Kind
- BOM column: counted (on the sheet) vs derived (from the recipe).
- Labor rate
- Your $/hr. Hours come from assemblies. You set the rate. Occupied / demo can apply a factor.
- Legend
- The project symbol list. It wins over a generic catalog. Teach a missed mark once.
- LF
- Linear feet. Raceway, wire, track, cable.
- Luminaire schedule
- Catalog (type and description). The lighting plan is the takeoff. Fixture dollars stay open until quoted.
- MC whip
- Metal-clad fixture whip. Usually 6 ft on a T-bar hang, fixture to box.
- Named revision
- A snapshot of the takeoff. Original vs this takeoff stay. Re-run does not wipe edited cells.
- OFCI
- Owner-furnished, contractor-installed. Material may be $0. Labor still exists. Do not hide it.
- One-line
- Riser diagram. Gear and feeder spec. It does not invent pipe length on the floor plan.
- Panel schedule
- Breaker and load list. Catalog, not a device count on the floor.
- Raceway
- The pipe: EMT, PVC, GRC. Plus couplings, connectors, straps, elbows, wire.
- Recap
- Bid summary: material, labor, quoted fixtures, misc, overhead, profit.
- RFQ
- Request for quote. Export the BOM in a file a distributor can upload.
- Scale
- Feet per drawing point. Confirm on the title-block scale and the bar.
- Shop book
- Your labor rate, vendor nets, and cell edits saved for the next job. Restore catalog defaults any time.
- Stamp
- Marks the letter as the print version. Cells stay editable. Change a qty and the stamp drops.
- Strap
- Conduit support. See hanger.
- T-bar
- Lay-in grid ceiling. The fixture is the box. Extra hangers only when the spec asks. Earthquake clips when the note says so.
- Takeoff
- The count: devices by type, measured raceway, derived fittings. Not the priced letter.
- Teach
- Click a missed glyph, name it, reuse that type on this job.
- THHN
- Building wire. Sized with the circuit tag (#12, #10, #8…) plus ground.
- UNKNOWN
- A blank material price. It stays open. It is not $0. Stamp is blocked until the quote is pasted.
- Waste
- Raceway only, typically 10%. Not applied to counted devices.
- Whip
- MC or FMC from the fixture to the box. Usually 6 ft on T-bar.